SHARING JERUSALEM "PROPOSAL"
THE TIME TABLE
There is little doubt that the proposed project
is delicate and complicated. A great deal of thought has been given to
establishing a viable work plan that will take into account potential difficulties
and ensure the smooth execution of the program within the next year, as
the situation in Jerusalem is tense and any delay under these conditions
will be counterproductive.
Preliminary Preparation ( October - December
1996)
During the next three months five key tasks will be completed:
- Establishment
and stuffing of the joint steering committee, the Palestinian and the Israeli
organizing committee, the professional sub- committees and the international
board.
- Preliminary planning
of key events and contact with potential participants.
- fundraising of
the full budget for 1997.
- Conclusion of
contracts with the producer and coordinators.
- Organization of
two small events in November and
December on the
main theme of the project.
Planning Phase ( January - may 1997 )
The first five months of the year will be devoted
to detailed planning of the June events. On the planning level, the final
program will be concluded in consultation with local and international
experts, at a joint meeting of the steering committee and the international
coordinating committee. On the organizational level, working groups composed and professionals voluntary associations and
volunteers will be formed. These groups will be responsible for specific
programming and for all the technical details related to the events. On
the logistical level. arrangements for performance and exhibition sites
will be made, as well as travel and accommodation provisions for visitors
and performers. on the public relation level, initial publicity brochures
will be prepared, and the selling of subscriptions started. And finally
,additional public meetings will be held to establish the required build-up
for the June program.
Implementation Phase ( June - July 1997 )
The months of June and July involve intense preparation
of the events, supervision to ensure their successful implementation and
immediate evaluation and financial assessment . These two months will be accompanied by professinal public relation activities,
including daily press releases and a summary press conference.
Follow- up Phase ( August - December 1997 )
The follow- up phase consists of three main components,
details of which will be decided upon in concluding meeting of the international
coordinating committee and the joint steering committee. First, the publication
of a summary catalogue and educational guide. Second, the formation and
registration of Sharing Jerusalem fund. Third, the preparation of specific
project proposal for ongoing cooperative activities.
A great deal of initial thought has already been
invested in the conceptualization and preparation of this project. Despite
the short timetable, it is possible, relying on the experience and qualifications
of the organizers, to carry out the program in its entirety within the
proposed time frame.
|