Brief No. 1; July 8, 1998
The
three decades of Israeli occupation in Bethlehem saw almost no
repair, upkeep, or modernization of the most basic infrastructure. A
District with over 150,000 inhabitants, Bethlehem urgently needs to
upgrade, develop, and maintain its utility networks. In order to
improve the quality of life for the local population and service the
needs of the over two million pilgrims and tourists expected to
visit Bethlehem in the Year 2000, an adequate supply of goods and
services is being readied. The resulting upgraded infrastructure
will also create a conducive environment for economic growth,
development, and job creation. Infrastructure networks will help
transform the Bethlehem region into a tourist destination appealing
to visitors with a wide range of interests.
The
Bethlehem 2000 Project Authority thanks
The United Nations Development Programme/ Programme of
Assistance to the Palestinian People - UNDP / PAPP Jerusalem
for
making the publication of this Information Kit possible
The Bethlehem 2000 Project is
Addressing the Needs of the Districts'
Infrastructure:
Water and Sanitation
Electrical Power Supply and Distribution
Solid Waste
Traffic and Transportation
- Six projects, including
the upgrading of a dilapidated water distribution network, a water
reservoir, the building of a sewage network and a sewage treatment
plant are upgrading existing water infrastructure. Inadequate
systems for waste water collection and degradation of the
environment are largely due to a lack of a waste water treatment
plant. The projects designed to upgrade and upkeep the water network
in the Bethlehem District are expected to cost US$23.25
million.
- Fifteen projects addressing the need to upgrade the electricity
system of the District are underway. Overloaded frail lines,
insufficient capacity leading to a large voltage drop, interruption
and poor reliability of power supply are being addressed through
these projects which will upgrade and modernise the Electrical Power
Supply System. The projects designed to modernise the system are
expected to cost between US$ 12-17 million.
- Five projects including a pilot waste management project, a land
fill project and the acquisition of needed equipment and management
workshops are addressing Bethlehem's need to modernise this public
service sector. The projects are estimated to cost US$ 5 - 5.2
million.
- Eleven highway and transportation projects, which include
extensive road repair, the establishment of pedestrian walk ways,
parking lots, and an upgrade of a street sign system are underway to
improve living conditions for the people of the District, tourists,
and pilgrims. The projects are estimated to cost US$60.5 million.
|