Palestinian National Authority Official Website
Peace Process

Time Line of

The Sharm-El Sheikh Memorandum

 

WHAT HAPPENED TO THE SHARM-EL-SHEIKH TIME-LINE ?

A- Palestinian Commitments:

No.

Palestinian –Commitments

Date of Implementation

1.

Monitoring and Steering Committee: Legal Committee, People-to-people committee, CAC, JEC,J.S.C, and other  Interim Committees

Will convene no later  than September, 13 1999. (Implemented)

2.

Collection of illegal weapons

On going – including reports.(Implemented)

3

Palestinian police lists

Ready to forward to the Israeli side no later than September, 13 1999. Review will start by the Steering and Monitoring Committee no later than October, 15 1999. (Implemented)

4

Arrest of suspected persons

On going , including reports.(Implemented)

 

B-Israeli-Commitments:-

No.

Israeli- Commitments

Date of Implementation

1.

7% C-B.

September, 5 1999. (Implemented)

2.

3% C-B, 2% B-A

November, 15 1999.(Not implemented)

3.

5.1% B-A, 1% C-A

January, 20 2000

4.

Start of the third phase of F.R.D committee

No later than September, 13 1999 (Not Implemented)

5.

Start the construction of Gaza harbor

October, 1 1999 (Implemented)

6.

Release of Palestinians prisoners, three stage of release.

  1. September, 5 1999 (Implemented)
  2. October, 8 1999 (Implemented)
  3. Before Ramadan 1999 (Not implemented)

7.

Opening of the safe passage northern and southern routes

Southern route- October, 1 1999 (Implemented) Northern route- January, 30 2000

8.

Carrying out the economic commitments relating to Israeli purchase tax, barriers to trade, and expansion of A1+A2. Lists, including reviewing the Paris Economic agreement.

To be implemented no later than October, 30 1999 (Not implemented)

9

Reactivating all standing committees established under the Interim Agreement, including the Monitoring and Steering Committee

To be resumed no later than September, 13 1999 (Implemented)

10

Completing the Hebron protocol, Shouhada Road, Hasbah, and new arrangements for the Haram Al-Ibrahimi

Shuhada road- October, 30 1999(Implemented)

11

Continuity committee – displaced person

To convene no later than October,1 1999 (Not Implemented)

12

Resumption of permanent Status negotiations

No later than September, 13 1999 (Implemented)

13

Conclusion of the P.S.N

No later than September, 12 2000

 

Front Page Back to Index